Thursday 17 March 2011

Fukushima nuclear plant owner falsified inspection records

THE Japanese owner of the stricken Fukushima nuclear plant falsified safety data and "dishonestly" tried to cover up problems there.

Tokyo Electric Power Co injected air into the containment vessel of Fukushima reactor No 1 to artificially “lower the leak rate”. When caught, the company expressed its “sincere apologies for conducting dishonest practices”.

The misconduct came to light in 2002 after whistleblowers working for General Electric, which designed the reactor, complained to the Japanese government. Another GE employee later confessed that he had falsified records of inspections of reactor No1 in 1989 - at the request of TEPCO officials. He also admitted to falsifying other inspection reports, also on request of the client. After that incident TEPCO was forced to shut down 17 reactors, albeit temporarily.

Mr Bridenbaugh told ABC News: “The problems we identified in 1975 were that, in doing the design of the containment, they did not take into account the dynamic loads that could be experienced with a loss of coolant.”

In a document entitled Lessons Learned from the TEPCO Nuclear Power Scandal, released by the company and seen by The Times, TEPCO blamed its “misconduct” in 2002 on its “engineers' overconfidence of their nuclear knowledge”. Their “conservative mentality” had led them to fail to report problems, the company said, resulting in an “inadequate safety culture”.

In 2007, TEPCO ran into trouble again after misinforming government officials about breakdowns at its Kashiwazaki-Kariwa plant, which had been damaged after a magnitude 6.8 quake. In a cable released by WikiLeaks, a US official said: “TEPCO issued a corrected statement on July 18 in which it admitted it miscalculated the amount of radiation leakage.”